Demolition is on track to close by 1 Nov. Joshi QA asked for epoxy bench tops, which adds 2 benches to the BOQ. Kabir's leave puts the MEP rough-in at risk; Sara to cover HVAC.
- Go with epoxy bench tops (pending QA sign-off)
- Sara covers HVAC ducting till 8 Nov
- Send lab bench spec v2 to Joshi QA3 NovAR
- Revise BOQ for the change order4 NovAR
- Confirm change order value with Nikhil5 NovAM
- Book crane for partition glass6 NovIS